Clashindarroch Wind Farm generates electricity for the very first time.

On January 23 at 2.40pm turbine number 18 generated first power from a wind speed of 7.8 metres per second (17 mph). Vattenfall and turbine supplier Senvion continue commissioning work on the remaining 17 turbines. Find out more information here.  

Christmas is fast approaching

Another Christmas is fast approaching on Clashindarroch, and unlike last year, it now looks like a wind farm! All turbines were installed through the summer – not too many issues thankfully – and internal fit out of each wind turbine carried out thereafter.  Since the end of the summer, commissioning works have continued and are […]

Turbine Deliveries – 8th September

On Monday 8th September we expect the following turbine component deliveries: • 1 convoy from Aberdeen The convoy will travel along the A96 and then A920, to site. Maps showing the routes can be found here. Should you have any queries about the process please contact me on Tel: 01434611300 or Email: Joanne.Hutchinson@Vattenfall.com    

Twelve turbines now installed

The site is really taking shape and we have now completed 12 turbines on site.   Should you have any queries please contact me on Tel: 01434611300 or Email: Joanne.Hutchinson@Vattenfall.com  

Turbine Deliveries – 4th September

On Thursday 4th September we expect the following turbine component deliveries: • 1 convoy from Aberdeen The convoy will travel along the A96 and then A920, to site. Maps showing the routes can be found here. Should you have any queries about the process please contact me on Tel: 01434611300 or Email: Joanne.Hutchinson@Vattenfall.com